You, the project manager, have worked out the resources required for each activity in the activity list, and now are ready to estimate activity durations.
All that you need to do now is to figure out the effort required for each of those activities, right?
No, I’m afraid.
This point can be a bit confusing. Read on.
Estimating Activity Durations process is about figuring out the effort required to complete each activity, AND the amount of resource required for the activity, AND figuring out how long does it take to complete the activity by combining these two.
Let us look at an example –
As we saw earlier John is managing a project of building a house for Josh. One of the tasks he has for the laying foundation is ‘Pour concrete footings’. John knows that for this activity he needs some amount of concrete, and a few people to pour the concrete into the trench.
In the project management activity of Estimating duration of Activities he will need to figure out the quantity of concrete and the number of people he needs for this task. Let us say that would be 800 cubic-ft of concrete and 6 people. He calculates that it takes 4 days for 6 people to pour and set 800 cubic-ft of concrete into the trench. Hence the duration for this activity would be 4 calendar days.
Duration is in calendar days (or hours, weeks – the unit of work chosen for the activity), and not raw the effort like number of person days. In short, Duration is not raw Effort.